Weekly early-morning continuous concrete pours at the Gateway site begin the first week of July 2024

June 26, 2024

Continuous concrete pours will occur weekly starting the first week of July 2024. To minimize disruption as much as possible, only the necessary amount of concrete will be poured each week while ensuring the structural integrity of the new building. On the days of continuous pours, crews will arrive at the project site at 3 a.m., and pumping will begin around 4 a.m. All trucks and pumps will remain within the project site. Each continuous pour will take approximately 13 to 14 hours and should be completed in the early evening. Please refer to the Letter to Neighbors distributed to residences along Hearst Avenue in June 2024 for the schedule of pours through the end of August 2024.

Please note that the construction schedule is subject to change and may be influenced by various factors, such as the weather.

For more information about the Gateway, please visit the project page on the Capital Stratgies website.

UC Berkeley Capital Strategies